How to show a Confluence roadmap by days or by quarters

By Jake Marsh · Updated

Confluence's built-in Roadmap Planner shows a roadmap by weeks or by months only. To show the same plan by days or by quarters, add a Milewell roadmap to the page and switch between Days, Weeks, Months and Quarters in its toolbar. The zoom changes the view for everyone; the dates on your bars stay exactly as they were.

Why the built-in planner stops at weeks

Atlassian's help page for the Roadmap Planner says you "choose to display it by weeks or months". A bar that lasts two days is hard to read at week scale, and a twelve-month plan is wide at month scale. There is also no today line to show where the team stands.

Steps

  1. Install Milewell from the Atlassian Marketplace on your Confluence Cloud site.
  2. Edit the page, type /Milewell and pick Milewell roadmap, then publish. The roadmap is edited on the published page from here on.
  3. Bring your plan in. If the page already has a Roadmap Planner, click Import Roadmap Planner or CSV, then Roadmap Planner on this page, and pick it. Lanes, bars, markers and the date range come across. Otherwise click Start blank and add lanes and bars.
  4. Click Days for a sprint or launch-week plan, or Quarters for a yearly roadmap. Weeks and Months sit between them.
  5. Click Today to scroll to the today line.
  6. Open View to set the rest of the calendar:
    • Show from and to fix the date range, or Fit to items lets the range follow the bars.
    • Week starts on picks Monday (ISO week numbers) or Sunday.
    • Working days sets which days count as work days. The others are shaded in day and week zoom.
    • On the chart turns the Today line and Dates on bars on or off.

Which zoom fits which plan

PlanZoomWhy
A two-week sprint or a launch weekDaysEach day has its own column, so a one-day task is a readable bar
A project of one to three monthsWeeksShows week boundaries, with ISO week numbers if the week starts on Monday
A half-year delivery planMonthsFits six months on one screen
A yearly product roadmapQuartersGroups the year into four columns for planning reviews

Bars can start and end on any day, weekends included, at every zoom. Shading a day as non-working only changes how it looks; it doesn't move any dates.

Moving dates at day scale

At Days zoom you can drag a bar's ends one day at a time, or select it and press the left or right arrow to nudge it a day (hold Shift to move a week). The dates in the panel on the right update as you go, and the change is saved a second after you stop.

What it costs

Milewell is $15 a month for up to 10 users, or $150 a year. From 11 users it is $1.50 per user a month, with lower rates for larger sites. Atlassian bills it, with a 30-day free trial. Install it and see every feature on the Milewell page, or read the Milewell documentation.

Milewell: Roadmaps and Gantt for Confluence

Roadmaps and Gantt charts on Confluence pages that save every change as a version, with dependencies, milestones and Jira links. From $15 a month for up to 10 users.


Questions

Does changing the zoom change the roadmap for everyone?

Yes. Zoom and the View settings are saved with the roadmap, so readers see the scale you picked. The bars' dates don't change.

Can people who only view the page change the zoom?

No. The zoom is part of the roadmap, so only people who can edit the page change it, and everyone sees the same scale.

Can the week start on Sunday?

Yes. Under View, set Week starts on to Sunday. Monday gives you ISO week numbers in the header.

What does the Roadmap Planner import keep?

Lanes, bars with their descriptions and page links, markers and the date range. The original Roadmap Planner stays on the page until you remove it.